Assign a work package to a budget (Costs plugin)

Note: assigning a work package to a budget requires installation of the costs plugin. The budget page is only available when the Budget module has been activated in the project settings.

In order to assign a work package to a budget select a work package, click the Show all button, click on the budget and assign a value from the dropdown menu. You can assign several work packages to the same budget.

Assign a work package to a budget

Note: This function can only be used if at least one budget was specified.

Time and cost units logged for this work package will be automatically deducted from the selected budget.